Bridge Project Will Close Route 1 for 15 Hours

CTDOT has announced that Route 1 will be closed in both directions, April 30 to May 1.

The Connecticut Department of Transportation announced today that Route 1 in Branford is scheduled to be closed to traffic to set new bridge girders for the Amtrak Railroad Bridge. There will be no access to north or south Route 1 between the I-95 on and off ramps at exit 53, referred to as the Branford Connector, and Route 142 (Short Beach Road). The closure is currently scheduled for 9 p.m. Saturday, April 30, until noon on Sunday, May 1.

The project, which began August 13, 2009, extends from Orchard Hill Road to the I-95 on and off ramps (Branford Connector). In addition to the installation of the new Amtrak Bridge, work will include the installation of a new box culvert at Mill Creek under Route 1; installation of new traffic signals at Alps Road, the entrance to the Branhaven Shopping Center and Route 142 along Route 1; and widening of Route 1 to provide more travel lanes along with improvements to drainage.

Motorist Advisory - Motorists are advised that they should plan ahead and seek alternate routes during the Route 1 closure. An info-line number, 203-315-0966, has been set up for the project that plays a prerecorded message with current project information including the hours of work and is accessible 24 hours a day, 7 days a week.
The CTDOT offers the following state road detours; the town will have local road suggested detours available closer to the date of the closure, which will most likely feature the use of Maple Street.

DETOUR INFO
Saturday, April 30, 9 p.m. until Sunday May 1, noon:

Route 1 southbound traffic will be detoured onto Branford Connector to I-95 south, exit 52 (Route 100, High Street/Main Street) and back onto Route 1 (West Main Street).

Find out what's happening in Branfordwith free, real-time updates from Patch.

Route 1 northbound traffic traveling between Route 100 in East Haven and Route 142 (Short Beach Road) in Branford will need to reroute onto southbound Route 1 to Route 100 to I-95 northbound to Exit 53 Branford Connector to U.S. Route 1 north.

LANE CLOSURE INFO
At all other times motorists can expect lane closures or alternating one way traffic on Route 1 during nighttime hours:

Monday - Friday 10 p.m. to 6 a.m.
Saturday 10 p.m. to Sunday, 9 a.m.
Sunday 9 p.m. to Monday, 6 a.m.

DOT Project No. 0014-0157 was awarded to J.F. White/Empire Joint Venture of Westfield Massachusetts on June 29, 2009 at a cost of $44,706,241.35 and is scheduled to be completed in March 2014.

The construction project is one of several transportation infrastructure initiatives being funded under the American Recovery and Reinvestment Act (ARRA). For more information on the American Recovery and Reinvestment Act of 2009 (ARRA) and a full listing of Connecticut DOT ARRA projects, please go to their website under the “Recovery Information” icon in the right hand margin.

Above information is a Press Release from the Connecticut Department of Transportation.

Find out what's happening in Branfordwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here